The Tripura HC has directed NHIDCL to submit its pending progress report by November 24 over delays and poor-quality national highway repairs, while seeking immediate corrective measures on damaged stretches of NH-108B and NH-208 following concerns raised by the state government.
The Tripura High Court has directed the National Highways and Infrastructure Development Corporation Ltd (NHIDCL) to submit its pending bi-weekly progress report by November 24, taking serious note of delays and concerns over the quality of ongoing national highway repair works across the state.
A Division Bench comprising Chief Justice M.S. Ramachandra Rao and Justice S. Datta Purkayastha passed the direction while hearing a suo motu public interest litigation concerning the condition, maintenance and repair of national highways in Tripura.
The court observed that NHIDCL had not submitted its mandatory bi-weekly progress report since October 14, despite an earlier direction issued on September 8. Accordingly, the Bench directed the agency to file the pending report by November 24 and ensure that a copy was served on the Advocate General in advance.
During the proceedings, the Advocate General presented the concerns of the state government’s Public Works Department (National Highways) regarding delays in contractual action, tendering procedures and the progress and quality of repair work on several highway stretches.
The state government supported NHIDCL’s administrative steps against defaulting engineering, procurement and construction (EPC) contractors, including their temporary suspension and the initiation of contract termination proceedings. However, it raised concerns over repeated delays in awarding contracts because of single-bidder non-responsiveness and technical disqualifications.
The High Court also expressed concern over these procurement-related delays and urged NHIDCL to streamline its tendering procedures to ensure that essential highway repair works are not unnecessarily held up.
The PWD placed particular emphasis on four highway packages requiring urgent attention.
For Package-II of NH-108B, covering the Mohanpur-Subalsingh stretch, the department highlighted serious structural and drainage damage identified by Special Observer Ravi Prasad. It stressed that temporary repairs should be followed by durable road construction to prevent further deterioration.
Regarding Package-III, covering the Subalsingh-Khowai stretch of NH-108B, the state government called for close monitoring of the existing contractor during the trial period. It also recommended immediate replacement if the contractor failed to meet essential road safety requirements.
For Package-IV of NH-208, covering the Srirampur-Bamanchara stretch, the PWD urged NHIDCL to accelerate temporary repair activities and expedite the appointment of a replacement contractor following the suspension and proposed termination of the existing contractor.
The most serious concerns were raised over Package-V, covering the Khowai-Srirampur stretch of NH-208. According to the state government, more than 64 per cent of this stretch was severely damaged, with deep potholes and distorted road surfaces creating significant difficulties for commuters.
The department warned that gravel-based temporary repairs could deteriorate quickly during heavy rainfall unless proper compaction and drainage arrangements were ensured. It emphasised the need for technically appropriate repair methods to maintain road safety and durability.
The state government also welcomed the observations of Special Observer Ravi Prasad and the inception report prepared by Intercontinental Consultants and Technocrats Pvt. Ltd. It recommended incorporating their findings into the detailed project reports, particularly regarding underground drainage systems, hill-cut stability, cross-drainage structures and proper road gradients.
| Also Read: EVM Commissioning Begins Under Tight Security Ahead of Agartala Civic Polls |
Additionally, the PWD insisted that NHIDCL’s additional field personnel remain physically present at construction sites to supervise the work being carried out by the alternative maintenance agency, J. Infratech Limited.
| Also Read: Tripura BJP president Confident of Victory in Upcoming Agartala Civic Polls |
Taking note of the concerns raised by the state government, the High Court directed NHIDCL to examine the observations and take appropriate corrective measures immediately.
The matter has been listed for further hearing on November 24, when NHIDCL is expected to submit its pending compliance report detailing the progress of highway repair works and action taken on the issues highlighted before the court.